Everything is now in place to begin construction.  Construction will be in four phases – a pre-volunteer phase followed by three volunteer phases (see table below).  Excavation of land began on May 1, 2008.  When volunteer Builders arrive on June 20, 2008, the basement and footings will be in place and building materials will be onsite.

Phase

Construction Task

Start Date

Pre-volunteer

Phase

Pre-volunteer Construction - excavation, utility hookups, underground mechanicals, footings, foundations, & slab

May 1, 2008

Volunteer Phase 1

Exterior Construction - rough framing, roofing, siding, soffit, fascia, windows, doors, rough-ins for plumbing, electrical, data, & HVAC

June 20, 2008

Volunteer Phase 2

Interior Construction -  insulation, drywall, painting, and flooring

August 1, 2008

Volunteer Phase 3

Finish Work - trim work, interior doors, cabinets, vanities, countertops,  finish plumbing, electrical,  data, HVAC, & landscaping

September 12, 2008














Volunteer Builders are either part-time or full-time Builders.  Most Builders are part-time Builders who come and build on Friday and Saturday.  Full-time Builders sign up for an entire week or more.

To become a Solid Rock Builder, just come to the building site. You don’t need to fill out any paperwork in advance.  You’ll be asked to sign a short application form when you arrive.  We start working at 7:00am on Thursday, Friday and Saturday.  Come whenever you can make it, and drive safely.  No work on Sunday.  Sunday service is at 10:00am at LandMark Center Auditorium,500 E Jefferson St, Viroqua, WI.

Bring your friends and family.  In addition to builders, we need all kinds of support people from supplying material to serving food. Come experience the awesome power of spiritual fellowship working shoulder-to-shoulder with other builders.

Grace Church Design

    Elevation Drawing of Grace Church

    Floor Plan for Level One

    Floor Plan for Level Two

    Site Plan Drawing

Resource Material

    Construction Schedule

    Road Map to Grace Church Building Site

    Hotels Near Grace Church

    Campgrounds Near Grace Church

Sunday Announcement Material

   
Solid Rock Builders Video  The video will download, Windows Media Player will start up, and the
     video will play.  After playing the video, go to the Windows Media Player menu “File” and “Save As” to
     your local hard drive. The file is 29 Mbytes in size, so you’ll want to be on a broadband internet connection.


    Bulletin Insert, 3"x8", Microsoft Publisher Format
    Bulletin Insert, 3"x8", PDF Format

    Bulletin Insert, 5"x7", Microsoft Publisher Format
    Bulletin Insert, 5"x7", PDF Format

    Response Card, PDF Format

    Cue Cards, Microsoft Word Format
    Cue Cards, PDF Format

Photos of Grace Building Project

    Ground Breaking Photos

    Excavation Photos

 

Solid Rock Builders Ministry is assisting in building Grace Church.  The church has been designed as a two-story building with a walkout basement to maximize space (8,800 square-feet) and reduce costs.  The church building has been modeled after the La Crescent, MN EFC church build a few years ago.  A thanks goes to Daniel Butterfield who as a volunteer designed the church building. 

The small congregation of Grace Church in Viroqua, WI has been without a church for 8 years.   Plans are in place to build a two-level 4,400 square-feet church (8,800 total) beginning in June 2008.  Volunteers from the Solid Rock Builders Ministry will help build the Grace Church.  Without volunteer help, Grace Church could not afford to build a church.